Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How do you change duration default to days?

1 reply [Last post]
Dan Harang
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 31 May 2017
Posts: 2
Groups: None

Hello

I use Powerproject 12 and when I enter the duration for a task and hit enter it defaults to seconds. Is there a way to make the duration column default to days unless another unit is entered?

I've tried formating cells, catogory duration and the time unit day with out result.

Replies

Mike Testro
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Dan - Welcome to planning plannet.

Right Click on the top of the duration column.

Select Table definition

Select duration in the dropdown

In the right hand panel find Overide Time Unit and select the one you want.

Best regards

Mike Testro