Show/calculate elapsed days between two tasks.

A
A. E. 👤 Member for 6 years 3 months

Is it possible for ASTA to count the total number of days between two tasks? IE, I have an 'implement detour' and a 'remove detour' task at the beginning and end of my project respectiely, with tasks in between, and I need to know how many days the detour will be in place for. Can ASTA tell me this, or do I just have to count it myself? Thanks!

P
Paul Harris 👤 Member for 25 years 2 months

You may use a Buffer Task and the calander that it is assigned to will be used to calculate the value of the gap.

Regards

Paul E Harris

Director Eastwood Harris

Publishers on Oracle Primavera, Microsoft project and Elecosoft (Asta)Powerproject books, videos and training material.

www.eh.com.au

Forum Sponsor

Top Posters

paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts