Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline Date Columns

2 replies [Last post]
Lee Mallek
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 27 Apr 2005
Posts: 24

Can anyone assist me in displaying baseline start and finish date columns in Powerproject?

Replies

Chris Rymer
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 11 Jun 2010
Posts: 32
Groups: None

The start and end date columns look at the project data when you first set them up. To point them at a baseline right click on the heading of the column and select Table Definition. Make sure the column you want to amend is selected in the left hand window. In the right hand window the Detail tab will show Live, click into here and select the baseline. This should be repeated for any column that you want to show baseline data.

Hope this helps

 

Chris

Mike Testro
User offline. Last seen 18 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Lee

Use the baseline option to show the bars in there own lines or set up start and end date columns that rela\te to the baseline.

Best regards

Mike Testro