How can I display cost centres columns

1 reply [Last post]
Dumitru Minciu
User offline. Last seen 12 years 47 weeks ago. Offline
Joined: 19 Feb 2010
Posts: 2

Hello,

How can I display cost centres conlumns  in the spreadsheet? Can somebody please help me with this information?
How can I display one or more cost center columnn to see witch is the cost allocated on an activity for each cost center - manpower, matherial, plant, transportation, gas - defined in the project costs folder in the library? 

Thank you!

Replies

Mike Testro
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Dumitru

Right click on a column > open table definition > add a column > scroll down to Cost > open Cost box on the right > select the cost head or All if you have a lost of cost heads > apply & close.

Best regards

Mike Testro