Hello Fellow Planners,
I created a contract baseline at the initiation of my project and i have progressed the project since then so activity bars have obviously shifted fowards and backwards. I want to display my baseline finish dates on the chart next to each activity to make it easier for my client to see where each tasks SHOULD have been finishing. But for some reason Asta is not allowing me to.
I usually right click on the bar>Format Bar Chart>Task, then go to the task data display. On the 'left data display' drop down, it allows me to select the same selections as the 'Add Column' function to display info on the chart. When i select finish, it only shows the finish dates of the task which are completed (100 Percent Complete), tasks that are still in progress are left blank. I want it to display the baseline dates so the finish date can be displayed whether the task has been completed or not.
Does anyone know how to do this? Or is there a reasonable alternative?
Thanks in advance!!!
Replies