Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Display Week Numbers

4 replies [Last post]
Lee Mallek
User offline. Last seen 10 weeks 1 day ago. Offline
Joined: 27 Apr 2005
Posts: 24

Does anyone know how to display week numbers for the duration of a project along the timescale in Powerproject?

The drop down menu does not give it as an option?

Replies

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Lee

Read what Chris told you and set the start date to zero at week 1.

It also helps if you set the same start date in File > properties.

Best regards

Mike T.

Lee Mallek
User offline. Last seen 10 weeks 1 day ago. Offline
Joined: 27 Apr 2005
Posts: 24

Many thanks for your replys.

It seems to show Week No. 1 as -1? and if you change it to the week before the print preview shows starting on Week No.2?

Has anyone encountered this?

Chris Rymer
User offline. Last seen 3 years 8 weeks ago. Offline
Joined: 11 Jun 2010
Posts: 32
Groups: None

Lee

Mike is correct about the elapsed unit but if you need to change the week 1 position, right click in the date zone and go to Properties. Go to the Date/Scale tab and change the date zero date to where you want week 1 to start from.

 

Chris 

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Lee

Right click the date zone - click Insert Line - select Elapsed Units

Move the line up or down to the required postion.

Best regards

Mike Testro