Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Week numbers in the date zone

2 replies [Last post]
Alex Hough
User offline. Last seen 4 years 46 weeks ago. Offline
Joined: 10 Apr 2017
Posts: 7
Groups: None

Hi all

I have a 30 week programme that has a 2 week shutdown over Christmas. The current week numbers in the date zone show it coming out as 32 weeks, is there any way to not show week numbers over the 2 week shutdown?

ie. up to week 5, then nothing for 2 weeks, then in January start from week 6?

Thanks in advance!

Alex

Replies

Alex Hough
User offline. Last seen 4 years 46 weeks ago. Offline
Joined: 10 Apr 2017
Posts: 7
Groups: None

Brilliant, that worked thanks Ben!

Ben Taunt
User offline. Last seen 51 weeks 5 days ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Alex,

In the Date Zone Properties (right-click within the Date Zone > Properties), the line currently representing your week numbering will likely state Type = "Elapsed Units", Time Unit = "Weeks".  If you change Elapsed Units to instead be "Working Units", it will reflect your folding calendar's exceptions.  You should then see the change you want in your date zone.

7064
date_zone.jpg

Best wishes,

 

Ben @ Powerproject