Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Summary Bar Progress

9 replies [Last post]
Ray Ferguson
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 16 May 2003
Posts: 12
I have a problem with a top-level summary bar containing several nested summary tasks, which contains individual tasks. The over all project is on programme apart from 1 nested summary bar containing tasks that are 2 weeks behind, however the top summary is only showing 3 days slip? I would expect the project to be more than 3 days behind over all.

I believe that the top summary bar is not recording its contents progress accurately? Is there anyway to check this?

Would the nested summary bars distort the result of progress on the top summary?
Thanks

Replies

Ray Ferguson
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 16 May 2003
Posts: 12
Many Thanks Iain & Mike,

I received a good explanation from Chris Rymer (Asta) who reassured me that my % was correct. Sorry it’s difficult to explain reason here, in words only.

Thanks Again!

Kind Regards

Ray
Mike Testro
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Iain

Welcome to Planning Planet.

You do have a point except that you cannot toggle between the methods in properties for individual tasks or summaries.

You can select two columns in the spreadsheet to compare the two.

My default is the simple Percent Complete option.

Best regards

Mike Testro
Iain McNab
User offline. Last seen 13 years 31 weeks ago. Offline
Joined: 6 Dec 2007
Posts: 3
Groups: None
Hi Ray

Could this have anything to do with the progress on summary bars being calculated by the "duration method" or the "overall method" which can be changed through File - properties.

I think the duration method is based on an activity week count whereas the overall method gives every activity the same %age weighting.

Apologies if this is not relevant, and i have picked up the wrong end of the stick.

Regards

Iain
Mike Testro
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Ray

I have just run a dummy progress on one my training modules that I am setting up and - on comparing the progressed bars and summaries with the "contract baseline"
there are significant differences.

When I filter on the critical tasks the same delay is constant.

On checking what caused the differences in the summary bars I have found:

1. Float is being used up.
2. Bars are going over holiday periods.

In fact it would be most unusual if the delay duration was the same on every summary bar.

I hope this helps

Best regards

Mike Testro
Ray Ferguson
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 16 May 2003
Posts: 12
Hi Mike,

Thanks, yes the end date moves out by 2 weeks, but i would have expected the summary bar to show a bigger delay. I have asked my colleague to have a look at it in V10 to see how its reacts.

I emailed technical services last week about it and am still awaiting a reply.

Thanks again
Mike Testro
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Ray

So your end date moves by the same amount of delay on the structural steel.

Sorry but I have no idea what is going on - I will try to re-create the problem.

Either contact technical support or maybe Andrew Willard will pick it up.

Best regards

Mike Testro
Ray Ferguson
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 16 May 2003
Posts: 12
Hi Mike,
The progress line is zig zag and there is no float as the item in delay task (structural steel) is critical.
Thanks

Ray

ps.
I read a rather complicated explanation on how progress figures are calculated on summary bars in the V11.2 release notes, which I didn’t understand.
Mike Testro
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
HI Ray

Is your progress drop down straight or zig zag?

Do the delayed tasks have any float?

Best regards

Mike Testro
Ray Ferguson
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 16 May 2003
Posts: 12
I guess i should have added, i am working with V11.2
I wonder is it something to do with the upgrade from V10 to V11