Copying summary tasks

2 replies [Last post]
munaf patel
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 27 Feb 2012
Posts: 3
Groups: None

Hi Mike,

 

I have a schedule with a summary task with sub tasks which have been color coded .

If I copy this summary task to another schedule the color coding on the individual subtask bars disappears.

can you advice please

Also you did mention that when you had another website you collectedsome info. on cds ?

Can I have details please?

Munaf

Replies

munaf patel
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 27 Feb 2012
Posts: 3
Groups: None

Thanks Mike

Mike Testro
User offline. Last seen 22 weeks 5 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Munaf - welcome to Planning Planet

When copying tasks to another project you will have to copy the codes as well.

In version 10 & 11 when you copy tasks from one programme to another you are given the option to copy codes - resources and calendars as well.

If you missed it then I would suggest that make the copy again and pick up the other object that you want to copy.

Alternativel you can go into the first library and copy the codes and paste it into the new project - but then you will have to allocate them onto the copied tasks yourself.

I had a website called Planning Academy where you could download tutorials for use of Asta PowerProject - this was abandone about 3 years ago.

My current website is www.expertdelayanalysis.com but the only download is my Ebook - Principles of delay analysis.

In future of you want my direct advce it is best to send me a private message.

Best regards

Mike Testro