Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Adjusting Baseline For Compensation Events

2 replies [Last post]
Chris Lothian
User offline. Last seen 1 year 15 weeks ago. Offline
Joined: 18 May 2007
Posts: 34
Is there a way to edit / add to a baseline in Asta?

With an existing programme, in MS Project (2003), you can add new tasks (ie. compensation events) and add a baseline to just those tasks, without reassigning the baseline to the whole project.

The purpose for this is to create a new target baseline, to compare agreed dates & durations (ie. 1st contract programme + agreed compensation events) with the actual dates & duration.

Or am i going about this in the wrong way?

The contract is NEC3 Option C

Replies

Mike Testro
User offline. Last seen 33 weeks 10 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Chris

In version 10 provided you have not tampered with the baseline programme you can select a new activity and use the "merge" function in the baseline / what if dialogue to add it to the existing baseline.

It doesn’t always work but worth a try.

If you want an entirely new baseline for just a few tasks then create a new baseline on "selected tasks only".

Best regards

Mike Testro.
muhammad anwar
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS
Chris,

In NEC3 your accepted programme is your contract progromme.You should baseline this programme before updating and impacting CEs. When you impact CEs you don’t need to create baseline for CEs at this revision. This will help PM to understand how CEs have affected agreed programme by contrasting baseline with plan.
Once your new revision is accepted then that is your contract programme and you will reset your baseline of new revised programme having CEs baselined.
This approach is a departure from previous versions of Contract forms and requires effort to convince old stalwarts of ICE & JCT where your first accepted programme is contract programme for the life of project(or PM sometimes out of generocity may allow you to revise it)
As for as Powerproject is concerned Mike can better help you.

Regards

Muhammad