Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Adjust start date when schedule has logic applied to it

3 replies [Last post]
Austin Robinson
User offline. Last seen 6 years 24 weeks ago. Offline
Joined: 17 Oct 2018
Posts: 4
Groups: None

Hello everyone, I am a construction student using asta to build a schedule for a project I am working on. Now, I have built the entire schedule start to finish, but unfortunetly I have forgotten to add my preconstruction tasks, which, are required for my project. I established the start date (Notice to Proceed) for 10/12/2018 and proceeded with my schedule logic. I would like to have the preconstruction tasks starting on 8/27/2018 and move in logical order on the schedule. However, every time I reschedule, it moves the start date of my precon tasks up to 10/12/2018 regardless of constraints removed and changing the start date in bar chart format tab. Please let me know if anyone can help. Thank you - Austin

Replies

Austin Robinson
User offline. Last seen 6 years 24 weeks ago. Offline
Joined: 17 Oct 2018
Posts: 4
Groups: None

Thank you Mike and Andrew. Those helped me.

 

Regards,

Austin

Mike Testro
User offline. Last seen 19 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Austin - Welcome to Planning Planet

You can also set week 1 as the works start date by right click the date zone and set the date for weeks 1.

Earlir dates will show as minus numbers.

Best regards

Mike T.

Andrew Willard
User offline. Last seen 4 years 9 weeks ago. Offline
Joined: 31 Aug 2013
Posts: 5
Groups: None

Hi

 

File-Properties-Advanced properties -change the imposed start date.

 

Also make sure the date of the project report date is the new date you want

 

Andrew