Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Help on drawing bars

2 replies [Last post]
Christine P
User offline. Last seen 10 years 25 weeks ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None
Please can someone help?

I am having trouble trying to draw bars the length I want them. I have a worksheet set up with the following in the date zone area Month, Day (1-31) and Time (Hours mins).

I am trying to make a bar go from 11:00 - 13:30 but will only let me do it either 11:00-13:00 or 11:00-14:00, it wont let me do it half way.

How do i draw a bar with half hours on them please?

Replies

Mike Testro
User offline. Last seen 19 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Christina

As Paul wrote you do need to set the programme time units to minutes to get the results that you require - there is usually a drop down menu on the "Standard" icon menu.

Also make sure that the work pattern in your callendar does not have any Non-Work periods in the time zone that you are looking at.

Finally make sure that any resources attached to the task have the same calendar - this can be done in the modelling dialogue by ticking the "Calendar as Task" box.

There will be a full description of how to apply these items in the Help directory.

Best regards

Mike Testro
Paul Harris
User offline. Last seen 2 years 3 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
You need to change your snap Options. Do a search in help for snap and it will tell you all about it.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.primavera.com.au