Formatting of bars over non-working time

M
Mike Testro 👤 Member for 20 years 5 months

Hi All



This is a problem with power project - you can only set non work folding against 1 calendar.



If I have multiple calendars I usually set the folding option to -None-.



By the way any curing time should be set on a 24hr 7day week calendar not just a 7day working week. Set the duration column to ed.



Best regards



Mike Testro

O
Ozkan Turgutlu 👤 Member for 17 years 8 months

you can also right click on the Format Bar Chart and choose the calendar background for multiple calendars (i.e. 7 days for concrete curing and 5 day working for normal activities)

L
Laurie Willis 👤 Member for 19 years 7 months

Thanks fot your help Gijs.



You were right, the problem was with the working pattern. There was a wrong work pattern assigned to the calendar. As soon as I set the right one, the formatting of the bars updated to what I wanted.



Thanks again!

G
Gijs Alferink 👤 Member for 18 years 1 month

Hi Laurie,



I don’t know if I understoof you correct.

But if you set the workpattern in your 7 days calendar there is no weekend exception so to my knowledge there wil be no weekend appearance on your barchart.

If you apply te 7 day calendar to the task.

I tried this and the 5 day calender tasks show the weekend and the 7 day calender shows no weekend.



I hope I understood you correct and have been of any help.

Forum Sponsor

Top Posters

Nigel Hussey
1 posts
James Williams
74 posts
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts