Planned Percent Complete

1 reply [Last post]
Laurie Willis
User offline. Last seen 12 years 16 weeks ago. Offline
Joined: 17 Oct 2006
Posts: 21
Groups: None
Hi

I’m back on one of my favourite topics again - the Planned Percent Complete complete. I’d thought I’d got my head round how it works, but it appears not!

Currently, I show Percent Complete next to Planned Percent Complete. I enter progress into the Percent Complete column and expect the Planned Percent Complete column to show what I should have done on today’s date. Instead the Planned Percent Complete is working to my Progress Period. How do I set the column to work to today’s date instead?

Thanks, Laurie

Replies

Mike Testro
User offline. Last seen 22 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Laurie

The easiest way is to set up your main programme as a "baseline" using the baseline wizard under the "file heading".

When you set up the Planned Percent Complete column you can select the results to come from the baseline programme.

You may need to go back to your first unprogressed programme to set up the 1st baseline and ten import it into your progressed charts.

Best regards

Mike Testro