Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

comparing Percent complete and Planned percent complete

3 replies [Last post]
Laurie Willis
User offline. Last seen 12 years 34 weeks ago. Offline
Joined: 17 Oct 2006
Posts: 21
Groups: None
Hi,

In my project I enter the progress of tasks using the Percent complete column. Next this I have Planned percent complete showing how much I planned to do by the current date.

What column should I use to show the difference or variance between these values?

I have tried using the Planned Percent complete variance column, but it doesn’t work as I think that it wants to compare values to a baseline, which I do not want to use.

Thanks, Laurie

Replies

Laurie Willis
User offline. Last seen 12 years 34 weeks ago. Offline
Joined: 17 Oct 2006
Posts: 21
Groups: None
OK thanks Alexandre.

I understand that really you should use baselines but was hoping for a quick solution. But if it can’t be it can’t be done.

Cheers, Laurie