S Curve

1 reply [Last post]
James Young
User offline. Last seen 13 years 42 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 71
Groups: None
Hi all, how do i produce an S Curve in powerprojects?

Regards,

J

Replies

Dave Crosby
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 8 Oct 2008
Posts: 79
Hi James,

There is a free Add-on for Powerproject called Progress Expert. You’ll want to install this Add-on and read the associated guide. It’s only about 1MB to download.

Any Australian folks reading this are welcome to contact me directly for a copy.

Cheers,

Dave.