Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Weekly S curve for progress

4 replies [Last post]
Paul Jones
User offline. Last seen 6 years 42 weeks ago. Offline
Joined: 13 Jun 2017
Posts: 3
Groups: None
Hi- any know how to set weekly s curves for progress reporting? Thanks

Replies

Ben Taunt
User offline. Last seen 51 weeks 5 days ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

And don't forget the new "EVA Reporter" export tool, which has superseded the older Progress Expert macro and is now included in all versions from 14 onwards...

Mike Testro
User offline. Last seen 22 hours 10 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Paul

Can be cost but the better measure is resource hours or even labour costs. days progress.

Another is planned days progress over actual 

Expenditure of cost is not a true reflection of progress.

I call this the Golden Tap Syndrome - A gold tap costs 100 time a chrome one and takes the same time to fit.

Best regards

Mike T.

Paul Jones
User offline. Last seen 6 years 42 weeks ago. Offline
Joined: 13 Jun 2017
Posts: 3
Groups: None
Thanks mike, is this done through the resource graphs set as cost centres?
Mike Testro
User offline. Last seen 22 hours 10 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Paul

You can set up any histgrams comparing planned with actual with a multiple set of data.

The graphs though are better presented on a spreadsheet when the data is exported.

Best regards

Mike Testro