Waste and clean water Treatment

Quantity Surveying and assistant in Contract management ., THEMELIODOMI S.A., Waste and clean water Treatment

START Date: 
November, 2000
END Date: 
May, 2005

THEMELIODOMI S.A.

Department of water and wastewater management

Rensponsibilities:

Supervision of subcontractorsQuantity Surveying and assistant in Contract management .
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
8000

Project Planner, BLACK & VEATCH International, Waste and clean water Treatment

START Date: 
June, 2007
END Date: 
December, 2008
  1. Refurbishments[Design, Supply, Installation, Construction, commissioning and testing]  Lane End WTW [3 million Pound starlings]

            Clients:Thames Water

  1. Refurbishments[Design, Supply, Installation, Construction, commissioning and testing]  

     Ashford STC [12 Million Pound starlings]

     Clients: 4 D

  1. pH Correction