Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Waste and clean water Treatment

Quantity Surveying and assistant in Contract management ., THEMELIODOMI S.A., Waste and clean water Treatment

START Date: 
November, 2000
END Date: 
May, 2005

THEMELIODOMI S.A.

Department of water and wastewater management

Rensponsibilities:

Supervision of subcontractorsQuantity Surveying and assistant in Contract management .
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
8000

Project Planner, BLACK & VEATCH International, Waste and clean water Treatment

START Date: 
June, 2007
END Date: 
December, 2008
  1. Refurbishments[Design, Supply, Installation, Construction, commissioning and testing]  Lane End WTW [3 million Pound starlings]

            Clients:Thames Water

  1. Refurbishments[Design, Supply, Installation, Construction, commissioning and testing]  

     Ashford STC [12 Million Pound starlings]

     Clients: 4 D

  1. pH Correction

Market Place

No results found... (try selecting a different content filter)

Syndicate content