Commissioning %26 Startup

Hookup & Commissioning Planner, BP Angola, Greater Plutonio FPSO

START Date: 
February, 2006
END Date: 
May, 2008

Development of the Level 3 integrated Hook-up,  commissioning and start-up schedule of approx 250,000 manhours. This included all interfaces with Sub-sea and FPSO  mooring activities including riser tie-ins, umbilical tie-ins and flexible riser connections.

Hook-up and Commissioning Planner, Technip, Dalia Mar Profundo -FPSO

START Date: 
February, 2005
END Date: 
February, 2006

Development of the Level 4 commissioning schedule including links to construction and pre-commissioning schedule. Schedule was resource weighted (approx 300,000 manhours) and broken down to subsystem level. Coding allowed direct updating from Certification system (ICAPS).

Reporting directly to the FPSO Commissioning Manager. Responsible for compilation and issue of Weekly and Monthly progress reports.