Hook-up and Commissioning Planner, Technip, Dalia Mar Profundo -FPSO
START Date:
February, 2005
END Date:
February, 2006 Development of the Level 4 commissioning schedule including links to construction and pre-commissioning schedule. Schedule was resource weighted (approx 300,000 manhours) and broken down to subsystem level. Coding allowed direct updating from Certification system (ICAPS).
Reporting directly to the FPSO Commissioning Manager. Responsible for compilation and issue of Weekly and Monthly progress reports.