Greater Plutonio FPSO

Hookup & Commissioning Planner, BP Angola, Greater Plutonio FPSO

START Date: 
February, 2006
END Date: 
May, 2008

Development of the Level 3 integrated Hook-up,  commissioning and start-up schedule of approx 250,000 manhours. This included all interfaces with Sub-sea and FPSO  mooring activities including riser tie-ins, umbilical tie-ins and flexible riser connections.