Project: Le Mirage Downtown (4B+G+M+10+Tech+PH) Mixed Use Building (Contract value: Qar 190 Million
Location: Doha, Qatar)Preparation of resource and cost loaded fidic clause 14 baseline schedule and getting it approved from client.
Updating the programme as per the progress at site, preparation of recovery schedules.
Preparation of Extension of time Claim by Time impact analysis.
critical path analysis of schedule at progress reporting. Various reports – DPR, WPR, MPR (preparation and
tracking).