PLANNING ENGINEER, Gulf Contracting Co WLL, Doha Festival City & Le Mirage Downtown

START Date: 
March, 2014
END Date: 
October, 2017
Project: Le Mirage Downtown (4B+G+M+10+Tech+PH) Mixed Use Building (Contract value: Qar 190 Million
Location: Doha, Qatar)Preparation of resource and cost loaded fidic clause 14 baseline schedule and getting it approved from client.
Updating the programme as per the progress at site, preparation of recovery schedules.
Preparation of Extension of time Claim by Time impact analysis.
critical path analysis of schedule at progress reporting. Various reports – DPR, WPR, MPR (preparation and
tracking).
Attending weekly meetings, progress review meetings.
Preparation of procurement schedules, drawings schedules, subcontractor/supplier procurement etc.
Prepares cash flow, charts and manpower histograms.
Verify critical path and interfaces between design/engineering/ procurement / execution.
Monitoring progress periodically and compares it with the baseline. Project: Doha Festival City (Contract value: Qar 1.2 Billion Location: Doha, Qatar)Preparation of Baseline programme - clause 14 Resource and cost loadedRegular weekly update of programme Supportng the lead sheduler in EOT claims with requisite documents.Preparation of DPR,WPR,MPR.Prepares cash flow, charts and manpower histograms.Critical path analysis in regular weekly updates and recording changes in schedule log.Attendng weekly progress meetings and supproting project manager with requisite data in delays.Alerting site team with potential delays and look ahead schedules.supportng the commercial team, QA/QC with procurement details, material submittals, prequalifications etc,.
Experience Hours (Planning & Scheduling): 
5500
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
500