Civil Site Engineer, Meimar Store Company, RESIDENTIAL VILLAS

START Date: 
October, 2013
END Date: 
December, 2014

Work As Site Engineer , execute ,reviewing and supervise labour and work at site .

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
150

Civil Site Engineer, Meimar Store Company, RESIDENTIAL VILLAS

START Date: 
October, 2013
END Date: 
December, 2014

Work As Site Engineer , execute ,reviewing and supervise labour and work at site .

Experience Hours (Planning & Scheduling): 
250
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
150

Assistant Manager - Planning Engineer, Samsung C&T Corporation, ROY HILL PROJECT – AU$11 Billion 55 Million tonne per annum Iron Ore Project in Western Australia.

START Date: 
April, 2013
END Date: 
November, 2016

Planning Engineer at Roy Hill Project in Australia.

Developed project baseline schedule.

Project progressing report.

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Forensic Analysis): 
900

Proejct Controls Engineer, Petrofac E&C International Ltd, Ruwais NGL Train 4 Project

START Date: 
November, 2011
END Date: 
July, 2013

November'11 to July'13 with M/s Petrofac Emirates, Ruwais, Abu Dhabi, as Engineer-Project Controls.

Project Title           :               Ruwais NGL Train 4 Project

Senior planning engineer, Ignalina Nuclear Power Plant, Decomissioning of INPP

START Date: 
November, 2009
END Date: 
December, 2012

Integrated decommissioning Program (Mega-project) activities maintaining (1-st and 2-d levels):

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
1550

Strategic planning group leader, Ignalina Nuclear Power Plant, Decomissioning project of INPP

START Date: 
December, 2012
END Date: 
May, 2014

Strategic planning group leader

Integrated decommissioning Program (Mega-project) decommissioning scenarios (what-if scenarios) developing. Modelling and studying of different negative impacts or restrictions on total cost and critical path. Among those are inflation impact, technical uncertainties, funding lack and others.  Developing new proposals for decommissioning strategy yearly update process.

Experience Hours (Planning & Scheduling): 
2150
Experience Hours (Cost Management): 
650

Senior Project manager, DPE, Dirección de proyectos Europeos

START Date: 
January, 2000
Project Manager Professional (PMP) Trainer in Project Management . Durang moré than 15 years I have been the CEO of a PMI Global Register Education Center. I had moré than 7.500 Professional students. Helping them to manage their Professional Projects.
Experience Hours (Planning & Scheduling): 
20000
Experience Hours (Cost Management): 
15000
Experience Hours (Forensic Analysis): 
10000

Senior Project manager, DPE, Dirección de proyectos Europeos

START Date: 
January, 2000
Project Manager Professional (PMP) Trainer in Project Management . Durang moré than 15 years I have been the CEO of a PMI Global Register Education Center. I had moré than 7.500 Professional students. Helping them to manage their Professional Projects.
Experience Hours (Planning & Scheduling): 
20000
Experience Hours (Cost Management): 
15000
Experience Hours (Forensic Analysis): 
10000

Advisor - Planning and Scheduling, Amey, Civil

START Date: 
May, 1996

Planning and controls management over a 35 year period with several major contractors in th UK and abroad

In addition , qualified with OND in 1982 ; again with BSc in 1986 and then with Phd in 1994 .

Similarly , progressed through the IOB from Student/Member/Fellow in the same timescales

Experience Hours (Planning & Scheduling): 
20000

Site Planner, Atkins Faithful & Gould, Jeddah, New King Abdul Aziz International Airport, Saudi Arabia

START Date: 
June, 2013
END Date: 
August, 2015

Site Planner – June 2013 to August 2015

Faithful+Gould, Project Control Department

Tel: +966 14628770 Fax: +966 14611790, www.fgould.com

 

Project: New King Abdul Aziz International Airport, Jeddah, Saudi Arabia

Client: General Authority of Civil Aviation. Saudi Arabia

Consultant: Dar Al Handasa Group

Main Contractor: Saudi Bin Laden Group

Experience Hours (Planning & Scheduling): 
3850
Experience Hours (Cost Management): 
3850
Experience Hours (Forensic Analysis): 
1000

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.