Decomissioning of INPP

Project engineer for Project management system implementation , Ignalina Nuclear Power Plant, Decomissioning of INPP

START Date: 
November, 2007
END Date: 
November, 2009

Assist in decommissioning management system and database project tender activities, commissioning, implementation. INPP project management system developing. Details and achievements:

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
500

Senior planning engineer, Ignalina Nuclear Power Plant, Decomissioning of INPP

START Date: 
November, 2009
END Date: 
December, 2012

Integrated decommissioning Program (Mega-project) activities maintaining (1-st and 2-d levels):

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
1550