Planning/Cost Engineer, AGAP Arabia Limited, Saudi Aramco, IPSA II (Iraq Pipeline Trans-Saudi Arabia, Phase II) On-Shore Marine Terminal for Company Oil Project (SCOP), Yanbu, Western Province, Saudi Arabia, Project contract

START Date: 
August, 1988
END Date: 
December, 1989

Construction of On-Shore Marine Terminal Unit  in Yanbu this terminal recieved oil from Iraq to the in-land pipieline.

Work involved preparation of daily and three weeks look-ahead schedule, weekly key quantity forecast, weekly accomplishment / productivity report, monitoring and updating construction schedule. Preparation of labor cost forecast and assist in the preparation of Project Cost Report. Maintain orderly cost and schedule records to provide project history and records for ensuring the integrity of the project cost and schedule and historical data

Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
250

Site Planner, Atkins Faithful & Gould, Jeddah, New King Abdul Aziz International Airport, Saudi Arabia

START Date: 
June, 2013
END Date: 
August, 2015

Site Planner – June 2013 to August 2015

Faithful+Gould, Project Control Department

Tel: +966 14628770 Fax: +966 14611790, www.fgould.com

 

Project: New King Abdul Aziz International Airport, Jeddah, Saudi Arabia

Client: General Authority of Civil Aviation. Saudi Arabia

Consultant: Dar Al Handasa Group

Main Contractor: Saudi Bin Laden Group

Experience Hours (Planning & Scheduling): 
3850
Experience Hours (Cost Management): 
3850
Experience Hours (Forensic Analysis): 
1000

Project Controls Manager, CCC (Consolidated Contractors Company), King Abdulaziz International Airport - Jeddah, Saudi Arabia

START Date: 
January, 2015

As a Project Controls Manager

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
2000

Assistant Planner or Planning Engineer, WorleyParsons Arabia Ltd., Haramain High Speed Rail Project - Jeddah, Saudi Arabia

START Date: 
June, 1987

More than 12 years of experience in Project Controls, Planning of project activities. Develop and maintain project baseline and current schedules for multiple projects.

Site planning enginner, Cemestero Saudi arabia co, KAFD Riyadh, Saudi Arabia

START Date: 
October, 2010
END Date: 
March, 2014

 Assisted the project managers in identifying the right resources for a project team, tracking resource allocation and resource usage to minimize, over and underutilization.  Identified & built project teams by using resources that belong to the Enterprise Resource Pool.  Performed in-depth reporting & analysis against completed projects, in-progress projects & resource availability.  Responsible for planning Day to Day erection Activity and Allocate resource accordingly.

Site planning enginner, Eversendai Engineering Saudi, Cemestero Saudi arabia co, KAFD Riyadh, Saudi arabia

START Date: 
August, 2011
END Date: 
December, 2013
 Assisted the project managers in identifying the right resources for a project team, tracking resource allocation and resource usage to minimize, over and underutilization.  Identified & built project teams by using resources that belong to the Enterprise Resource Pool.  Performed in-depth reporting & analysis against completed projects, in-progress projects & resource availability.  Responsible for planning Day to Day erection Activity and Allocate resource accordingly.  Coordinated with Client, Designer, Subcontractors, Quantity Estimation, Preparing Monthly Payment & Control in Do

Sr. Project Planner / Scheduler, Thermax India Ltd., Samsung Engineering A/c Takreer, Ruwais, UAE, Daelim Industrial Company A/c Saudi Elastomer, Saudi Arabia

START Date: 
May, 2010

 

Ø  Responsibilities:

1.       Project Schedule preparation using Primavera P6 and MS Project 2010.

2.       Defining Project Scope, Execution Philosophy and Risks mitigation plan.

3.       Data collection and schedule optimization based on functional progress reports.

Project Controls Manager, ABB Lummus Global B.V., Kemya Olefins Project, Al Jubail, Saudi Arabia

START Date: 
February, 1998
END Date: 
April, 2000

Project Controls Manager, Al Jubail Petrochemical Co., Kemya Olefins Project, Al Jubail, <?xml:namespace prefix = st1 />Saudi Arabia. Lump sum turnkey grass roots 700,000 MTA ethylene plant.

Planning Engineer, Saipem S.p.A., Construction of Gas Oil Separation Unit at Manifa ARAMCO Project, Working with Main Contractor SAIPEM, Saudi Arabia

START Date: 
July, 2003

My career in this line started in the year 2003  i.e over 7 years of Experience in Project Planning & Scheduling and Project Controls in Oil & Gas and Fertilizer industry.