Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Romania (EU.RO)

DAMBOVITA CENTER: www.plazacenters.com/casa_radi Project Controls Engineer

START Date: 
March, 2008
END Date: 
February, 2009
As Project Controls Cost Analyst at Plaza Centers for Dambovita Center Project specific duties and job responsibilities include:
– Setup and implement the Change Management Procedure to control all the project deviations;
– Setup Cost Models of executed project by Plaza Centers;

Washington Group International Project Controls Engineer

START Date: 
July, 2007
END Date: 
March, 2008
As Project Controls Cost Analyst at Washington Group International for Areva Imouraren Uranium Feasibility Study specific duties and job responsibilities include:
– Reconcile the current budget by task, by discipline with the estimated budget.
– Work with discipline leads, project engineer manager and project manager to create the logical links for the activities in the schedule.
– Setup the Engineering Progress Curves and Histograms for reporting.
– Setup the Earned Value Matrix for reporting.
– Report weekly the man-hours spent.

Washington Group International Project Controls Engineer

START Date: 
July, 2005
END Date: 
December, 2006
As Project Controls Cost Analyst at Washington Group International for Common Sulfur Project (CSP) in Bucharest, Romania, specific duties and job responsibilities include:
Common Sulfur Project duties:
– Keeping the Head of Project Controls Department and Project Controls Manager (when applicable) informed in detail of progress and costs achieved against plans. Gives’ early warning of potentially unfavorable trends and monitors the activities for mitigation.
– Setup the Quantity Tracking System.

SERACOM ENGINEERING S.R.L.: www.seracom-intern Assistant Planner

START Date: 
December, 2004
END Date: 
July, 2005
Project Management activities I took part: Bid evaluations, Kick of Meeting Report, Work Breakdown Structure-WBS, Cost Breakdown Structure-CBS, Project planning and scheduling, Earned Value Management indicators, Resource Cash-flow planning, SWOT Analyses, Stakeholders Analyses and Stakeholder Management;
– Participating at meetings and giving the technical information necessary for Bid Request, Offer or Contract;

IRIDEX GROUP CONSTRUCTII S.R.L.: www.iridexcons. Civil Engineer

START Date: 
September, 2004
END Date: 
December, 2004
Following and tracking of the Contract on all its course with the following responsibilities:
– tracking and responsible for good evolution of all the co-ordinated works from technical and financial point of view;
– Informing the Upper Management about the status of the contract;
– To petition the Investor for contract documentation, checking the execution documentation;
– Studying the contract, technical demands and execution documentation;
– Following all the financial guarantee clauses of the contract to be accomplished;

Damen Shipyards Galati Planner

START Date: 
June, 2010
Current Role

enka Planner

START Date: 
April, 2010
Current Role

START Date: 
April, 2010
Current Role

Washington Group International Planning Manager

START Date: 
June, 2000
END Date: 
April, 2002
Implementing established policy, procedures, and systems.
Provide functional and administrative management of all project control activities including: budgets, code of accounts, cash flow forecasts, manpower forecasts, progress and performance measurement, productivity analysis, trends, change control process, project and executive reporting.
Maintain adequate level of personnel, with appropriate levels of skills.
Provide on-going staff development and training.
Oversee the Cash Flow Analysis preparation for the Corporate reporting

Washington Group International Planner

START Date: 
December, 1998
END Date: 
June, 2000
Develop, maintain and control the project schedule; monitor and control the budgets and the costs, manpower forecast, progress, earned value and performance factor analysis for engineering phase.
Issue the internal and the Client (external) reports, invoice verifications; issues change orders and trends for all deviations from the budget..