Project Control Manager | Superintendent, PT. WAHANAKARSA SWANDIRI - CONSTRUCTORS, CHEVRON - EPC-Pungut Gathering Station & Water Distribution Project; Resource Unit Rate (CS-RUR-B) Projects; and Work Unit Rate (CS-WUR-D) Projects

START Date: 
February, 2008
END Date: 
December, 2011
  • Assigned to various projects: Pungut GS and Water Distribution - EPC Services [Contract No.8698-OK];  SLS-Resource Unit Rate Package-B (CS-RUR-B) - Construction Services [Contract No.8546-OK]; SLS, SLN, HOOU & CPM-Work Unit Rate Package-D (CS-WUR-D) - Construction Services [Assignment to PT.
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
8000
Experience Hours (Forensic Analysis): 
8000

Praveen Dayal

First Name: 
Praveen
Last Name: 
Dayal

Praveen Dayal is an accomplished IT management professional, has over 22 years of Program and Project Management, Information Security, IS Audit, Regulatory Compliance, Risk Management, Business Continuity, IT Operations and Service Delivery experience, worked with Public and Private undertakings of all sizes, held various organizational and administrative responsibilities as Vice President, Assistant General Manager.

Professional Since: 
May-1988 (36.9 yrs experience)
Oldest experience: 
Oct 1988 (36.5 yrs experience, WARNING: 0.4 years variance with Professional Since)
Years Experience: 
23

Project Manager, Comsoft Pte Ltd, Banking & Finance, Sales order and Accounting

START Date: 
February, 2005
  • Managing direct activities for product development, delivery & support. Acting as a single point of contact for incident and problem resolution for large clients. Driving continuous service improvement plan within the customer and delivery team.

     

Mr HK

First Name: 
Mr
Last Name: 
HK
Professional Since: 
Mar-1990 (35.1 yrs experience)
Years Experience: 
0

Project Engineer / Responsible Mechanical Engineer, Enexco Teknologies India Limited, PT Semen Andalas, Lafarge Group

START Date: 
March, 2006
END Date: 
December, 2006

 

·         Basic responsibilities includes erection, commissioning and troubleshooting of Company manufactured/ supplied machineries mainly for cement plant, like Wagon Loader, Rotopacker, Long Belt conveyors, Truck Loader, Equipments for silo extraction system like air slides, manual gates, Flow control gates etc.

·         Installed 2 nos. Wagon Loader inLAFARGE INDIA, JOJOBERA, JHARKHAND.

Senior Development Planning Engineer, ConocoPhillips Indonesia, Onshore and Offshore

START Date: 
March, 2012

Responsibilities:

- Prepare and develop schedule, man-power loading and risk assessment of different concepts for the FEL-0 up to FEL-3 activities and work closely with estimator and development engineers.
- Support of Scenario Planning for Field/Block development, identification and delivery of field development milestones and deliverables.
- Facilitating opportunity framing, concept identification, concept selection and others as required for Development Engineering teams and Be an effective focal point for the Development Engineering to

Victor Basa

First Name: 
Victor
Last Name: 
Basa
Professional Since: 
Jul-2004 (20.8 yrs experience)
Oldest experience: 
Jul 2004 (20.8 yrs experience)
Years Experience: 
7

Senior Planning & Project Control Engineer, ConocoPhillips Indonesia, Onshore and Offshore

START Date: 
August, 2011
END Date: 
March, 2012

Responsibilities:

  • Develop planning and scheduling, progress measurement and progress reporting requirements and to incorporate them into the Tenders / Agreements (FEED, EPC)
  • Depth-in review and analysis of all submittals from contractors related to planning, scheduling, progress measurement, reporting, time analysis, project resource loading, critical path, productivity, compliance with work breakdown structure, production of 'what if scenario, individual plan to suit both COPI, BP Migas and Contractors, includes verification of

Assistant Engineer / Document Controller, Fluor - Tripatra Consortium, Gametri Tirta Lestari Co. LTd, Flexible Program Management

START Date: 
May, 2004
END Date: 
December, 2011
1 June 2010 – Now

Fluor - Tripatra Consortium, Co. Ltd– Duri

Flexible ProgramManagementII & III

Position :   Document Control

 

 

 

Project Highlights,

 

Farid Ilyas

First Name: 
Farid
Last Name: 
Ilyas
Oldest experience: 
Feb 1996 (29.2 yrs experience, WARNING: 26.1 years variance with Professional Since)
Years Experience: 
41

Market Place

No results found... (try selecting a different content filter)

Syndicate content