Engineer / Project Engineer, ConocoPhillips Indonesia, (various projects)

START Date: 
July, 2006
END Date: 
October, 2014

project engineer, development engineer for both onshore and offshore projects

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
50

Engineer / Project Engineer, ConocoPhillips Indonesia, (various projects)

START Date: 
July, 2006
END Date: 
October, 2014

project engineer, development engineer for both onshore and offshore projects

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
50

Engineer / Project Engineer, ConocoPhillips Indonesia, (various projects)

START Date: 
July, 2006
END Date: 
October, 2014

project engineer, development engineer for both onshore and offshore projects

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
50

Engineer / Project Engineer, ConocoPhillips Indonesia, (various projects)

START Date: 
July, 2006
END Date: 
October, 2014

project engineer, development engineer for both onshore and offshore projects

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
50

Engineer / Project Engineer, ConocoPhillips Indonesia, (various projects)

START Date: 
July, 2006
END Date: 
October, 2014

project engineer, development engineer for both onshore and offshore projects

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
50

Madelin Hardjapamekas

First Name: 
Madelin
Last Name: 
Hardjapamekas
Oldest experience: 
Jul 2007 (17.5 yrs experience, WARNING: 37.5 years variance with Professional Since)
Years Experience: 
47

Sr. Cost Control Specialist, ConocoPhillips Indonesia, Gas Compression

START Date: 
July, 2007

10 years experience as cost control specialist. Prepare, maintain, and monitor project budget and forecast to complete project on budget. Prepare Monthly, Quarterly, and Long Range Plan Cost Report to different internal & external counterparts.

Moekti Arffandy

First Name: 
Moekti
Last Name: 
Arffandy

 Be a professional who in charge on Planning, Scheduling, and Risk Issues. Have extensive work experience in the preparation of work plans, schedule, risk analysis and monitor works for Pre-FEED, FEED, and Execution of Offshore and Onshore for oil & gas facilities.

And serve with valuable report and document which support for management information as used by management.

Professional Since: 
Sep-1997 (27.3 yrs experience)
Oldest experience: 
Sep 1997 (27.3 yrs experience)
Years Experience: 
20
Guild Accreditation: 
Awaiting Applicant

Lead Planning Engieer, ConocoPhillips Indonesia, Various Capital Projects

START Date: 
November, 2005
  • Compile, obtain approval of, analyse and update the portfolio ConocoPhillips Indonesia Projects
  • Coordinate schedule risk analysis
  • Develop and update ConocoPhillips Indonesia Project Services Procedure/Specifications
  • Assits Manager Project Services in enhancing Project Control System
  • Develop Planning Engineer
Experience Hours (Planning & Scheduling): 
24200
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
24200

Planning Engineer, ConocoPhillips Indonesia, Letang Tengah Rawa Optimization Project

START Date: 
September, 2011

As Planning Engineer with responsibility :
- Update Primavera P6 Schedule and Risk Register
- Review Contractor schedule, progress and report
- Provide overall planning, scheduling and progress reporting structure for Projects Management Team
- Liaise and coordinate planning information
- Provide planning and scheduling support during the development of bid documents and evaluations
- Advice to Project Management Team regarding all aspects of Planning, scheduling and progress reporting