Assistant Engineer / Document Controller, Fluor - Tripatra Consortium, Gametri Tirta Lestari Co. LTd, Flexible Program Management
Fluor - Tripatra Consortium, Co. Ltd– Duri
Flexible ProgramManagementII & III
Position : Document Control
Project Highlights,
This project covered all aspects of Chevron Pacific Indonesia-CPI’s portfolio of construction and maintenance work.
My experience :
· Compile and Analyze CPI’s Contractors payment progress include project cost, schedule, specifications, calculations, manuals, etc.
· Coordinate and keep track of all permits, licenses and certificate related to projects
· Responsible to enhance / upgrade system to keep pace with the changing business environment
· Establish an efficient Document Control system and procedures (based on best practices from other projects) and ensure proper utilization of the system.
· Develop Centralize filling system
1 July 2008 – 31 May 2010Fluor - Tripatra Consortium, Co. Ltd– Duri
Flexible ProgramManagement
Position : Document Control
Project Highlights,
This project covered all aspects of Chevron Pacific Indonesia-CPI’s portfolio of construction and maintenance work.
My experience :
· Work closely with Client’s representatives and their Contractor related to Engineering, QC and Construction, coordinate the resolution of contractual financial disputes and management of change.
· Coordinate and keep track of all permits, licenses and certificate related to projects
· Compile and Analyze CPI’s Contractors payment progress include project cost, schedule, specifications, calculations, manuals, etc.
· Temporary assignment as Scheduler
February 2007 – June 2008PT Tripatra Fluor - Duri
Oil & Gas ContractorFPM Project
Position : Task Force(Maintenance)
Project Experiences,
§ Active participate in building new Contractors Invoice Track System and standardize TF Subcontractors Claim.
§ Receiving progress claims and Progress Reports from TF’s Subcontractor and checks its completeness.
§ Analyze and negotiate with contractors to resolve all payment terms, conditions and pricing issues
§ Actively Coordinate communications during the payment process.
§ Monitoring, reporting, analyzing and managing the all project execution progress against time, milestones and invoicing schedule agreed in the customer contract by tracking logbook.
§ Maintenance the filling system of TF progress payment (for corporate)
May 2004 – 2007PT Gametri Tirta Lestari – Duri
Oil & Gas Contractor
Position : Project Administrator
Project experiences,
§ Project Administrator, ‘Waste Handling Contract Services’, (CPI WMT) Team,
§ Accounting Analyst, ‘Maintenance Waste Ex. Mud Drilling Services’(CMTF) project at PT Caltex Cond Mon Engineer on Condition Pacific Indonesia
§ Project Administrator, in ‘Industrial Hygiene and Gas Detector’project at HO – OU Duri Field , Bangko, Balam Area.
§ Project Administrator, in ‘Geo Scanner a Pilot Project’at HCT Bekasap Duri PT Chevron Pacific Indonesia.
§ I also experienced as HRD Support Team, Data Management, IT Support.
Skillexperiences,
§ Leadership and Management Skill
§ Produces Executive Report to Site Manager and Client (CPI)
§ Improve S-Curve, Accrual and Earn Value, Managing schedule (Primavera 3.0 and MS-Project) combine with MS Excel.
§ HR Experience, preparing employees salary, tax, consultation.