Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

(various projects)

Core senior Planner, Alstom Power Centrales, (various projects)

START Date: 
October, 2007
END Date: 
December, 2009

Initially engaged for the Turbine Supply and Installation Contracts for Medupi and Kusile Power Stations (South Africa) but eventually stationed in Belfort, France and deployed to as Utility Planner on projects and bids in Canada(Greenfield), Bulgaria(Greenfield), Saudi Arabia(Greenfield) and South Africa(Brownfield) within the following Phases:
Sales - Tender Time Schedule Development.
Execution - Client Contract Schedule (on award)
- Internal Project Integrated Control Schedules
- System Time Schedules
Key Performance Areas:

Experience Hours (Planning & Scheduling): 
4350
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
200

Core senior Planner, BARRON ENGINEERING / COFLEXIP SENNA, (various projects)

START Date: 
January, 2004
END Date: 
March, 2005

Refurbishment of Omega Oil Rig - Cape Town responsible for:
WBS Development.
Creation of Level 4 Integrated Project Schedule.
High-Level Key Date Contract Schedule
Engineering & Procurement Planning.
Resource Planning.
Alignment of Key Deliverables with Contractual Requirements.
Evaluation and Integration of Supplier Programmes.
Interface Identification and Management during execution.
Trend and Delay Analysis
Monthly Progress Reporting.
Recovery Planning.

Experience Hours (Planning & Scheduling): 
2400

Planner, Rockwater, (various projects)

START Date: 
August, 1993
END Date: 
March, 1995

Project planner for various internal/ external Projects, including launch and recovery systems, pipeline bundles, umbilical installation

Technical Assistant to VP for Operation / Site Project Engineer, P&Z Brobio Plumbing Contrs., Inc., (various projects)

START Date: 
July, 2001
END Date: 
March, 2003

As Technical Asst. to VP-Operations:

Assigned to main office and was task to assist the VP for Operations on the technical aspects of the different works at hand. Company representative for project site visits, pre-bid conferences technical/management meetings and the like. Preparation of bid proposal package for all prospective projects. Preparation of variation/ change order cost proposals for on-going projects. Assigned as Project Engineer for small projects & completed projects under warranty period.

Assistant Project Engineer, SHJ Development Corporation, (various projects)

START Date: 
January, 2001
END Date: 
June, 2001

As Assistant Project Engineer, I have assisted in the revision/drafting of all construction plans & other details for a forty (40) hectares subdivision using AutoCAD 2000 software. I was also assigned to supervise in the construction works of some specific area of the project which includes surveying works like differential & profile leveling.

Assistant Planner (Build & Construction), Willmott Dixon, (various projects)

START Date: 
March, 2009

I have day to day experience of tender programming my own projects using Microsoft Project, site logistics planning, material take offs, cost calculations, 3D logistic plans, live programme tracking and scheduling, client interviews and presentations.  I also have a basic understanding of Asta PowerProject, which I believe I could learn to use proficiently very quickly.

I also have experience of tracking progress of programmes on live construction sites.

I successfully completed a three year graduate management training scheme within Willmott Dixon Construction in which

Civil Engineer, BESIX, (various projects)

START Date: 
October, 2008

Experience in the planning and/or methods for the following types of projects:

  • Marine Works (jetties, MOFs)
  • Civil Engineering (transport infrastructure)
  • Buildings (high & low rise buildings in education, commercial and sports sectors)

Markets include:

  • Belgium, Netherlands, Australia, Egypt and Qatar

Activities include:

Planning Engineer, North East Shipbuilders Ltd., (various projects)

START Date: 
August, 1984
END Date: 
July, 1988

Responsible for unit outfit work packages for all production areas. Modular pipe work systems were split into work package information to enable 50 tonne modules of pipe work to be assembled offsite and then be installed as a complete unit. Also 500 tonne accommodation units were work packaged in a similar manner and fabricated on the quayside and lifted upon the vessel as a complete finished unit. Work packaging of this nature was developed during the construction of the I.T.M. "Challenger" which is a 45,000 tonne Crane Ship - the largest of its type in the World.

Mechanical Engineer, North East Shipbuilders Ltd., (various projects)

START Date: 
September, 1978
END Date: 
July, 1984

Responsible for the installation of ships engines, auxillary equipments and marine systems on merchant vessels

Senior Planning Engineer, Matthew Hall M&E Engineers Ltd., (various projects)

START Date: 
August, 1988
END Date: 
September, 1989

Project: Head Office
Responsible for the development of Artemis 2000 and Artemis Project Planning Systems within the Planning Function. Preparation of Tender Programmes and Construction Programmes for Mechanical / Electrical / Instrumentation work packages for Oil-fired Power Stations, food processing plants, gas handling plants, oil refineries, nuclear power station, paper mills etc.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content