Alstom Power Centrales

Core senior Planner, Alstom Power Centrales, (various projects)

START Date: 
October, 2007
END Date: 
December, 2009

Initially engaged for the Turbine Supply and Installation Contracts for Medupi and Kusile Power Stations (South Africa) but eventually stationed in Belfort, France and deployed to as Utility Planner on projects and bids in Canada(Greenfield), Bulgaria(Greenfield), Saudi Arabia(Greenfield) and South Africa(Brownfield) within the following Phases:
Sales - Tender Time Schedule Development.
Execution - Client Contract Schedule (on award)
- Internal Project Integrated Control Schedules
- System Time Schedules
Key Performance Areas:

Experience Hours (Planning & Scheduling): 
4350
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
200