Area Planning Manager, Weerasooriya Builders (Pvt) Ltd, Building, roads, Bridges & Infrastructure and High rise Building

START Date: 
June, 2011
END Date: 
April, 2018
  • Coordinates construction planning, schedule, budget cost analysis and technical submittals of the projects
  • Coordinates material, tools and equipment and ensure the delivery within the baseline program.
  • Coordinate with the project manager the developments of contract and baseline program Monitor and update actual project status with the target or baseline program and regularly update the project manager regarding project progress
  • Supervise and preparation of periodic billings and invoices up to approval of clients and ensure timely submissi
Experience Hours (Planning & Scheduling): 
2400
Experience Hours (Cost Management): 
2450
Experience Hours (Forensic Analysis): 
900

Planning Engineer, Al Naboodah Construction Group, Infrastructure Works such as Sewerage,Storm Water,Pump Station,Roads

START Date: 
November, 2015
END Date: 
May, 2017

·         Collecting and compiling of project progress data from respective engineers.

·         Develop the detailed baseline programme with resource and cost loaded .

·         Preparation of weekly/Monthly Progress reports with Variance (Planned V/s Actual), KPI & Milestones Delays.

Experience Hours (Planning & Scheduling): 
3800

Engineering Aide / Junior Planning Engineer, ECBALES Construction, Manpower Services & Supplies and CCF Employment and General Services – California Energy CASECNAN Water & Energy Company, Bridges & Buildings, Design of Pontoon, Hydroelectric Plant mainte

START Date: 
November, 2003
END Date: 
August, 2006
Recommends solutions to field problems that mayarise during construction.• Provides technical services such as specifications anddrawings.• Plans activities chronologically from start up to thecompletion of the project.• Prepares PERT – CPM of work activities.• Prepares cost estimates and materials take-off.• Supervises work in the field of ongoing construction.
Experience Hours (Planning & Scheduling): 
9700
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
300

Quantity Surveyor / Planner, Advanced Construction Co., Bridges, Roads, Government Buildings

START Date: 
August, 2008
END Date: 
August, 2011

Worked at the Main Office as a Office Engineer:Scope of work consist of preparation of estimates for the proposed construction projects that includes bridges, sewage system, underpass, and government office buildings. Prepares documents for project bidding. Define and propose construction schedule.

Lead Shutdown Planner, Flour - SKM Joint Venture (FAST JV), BHPIO Port Hedland Inner Harbor Project ($10B) – Bridge, Roads, Piling, Structural and Site Development

START Date: 
August, 2012
END Date: 
August, 2013

Responsible  for  coordination  and  integrationof  Shutdown  work  package  schedules  and  provided  progress trackingand reportingonadaily basis.Provideplanningsupportinthedeliveryofcommissioningplans and work integrationacrosscomplexscopeinterfaces.Supervisescontractors inensuringprogressreports&construction schedulesaredeliveredasspecifiedandontime.Consolidatecontractor'sreportsforinternalandcorporate purposes.

Construction Planners / Planning Engineers, Georgiou Group Pty Ltd., Pipeline, Land Developments, Roads, Bridges

START Date: 
October, 2013

Member of a Project Control Team for a Construction Group and dealing with Roads & Bridges, Bulk Civil Works, Pipeline Works, Land Development etc.

Planning & monitoring the projects starting from Tendering stage till the finish stage. Dealing with weekly reporting and detailed productivity analysis to track the project. Early warnings for future conflicts or issues, Dealing with EOt Claims & associated Costs.

Experience Hours (Planning & Scheduling): 
1800
Experience Hours (Forensic Analysis): 
100

Engineer - Senior Planning, Boom Construction Co., Roads

START Date: 
October, 2014

Preparation of Baseline Programme, Progress Monitoring and Update, Extension of Time.

Experience Hours (Planning & Scheduling): 
20000

Senior Quantity Surveyor/Contract Administrator, Ministry of Works & Transport, Bahrain, Roads, Bridges and High Pressure Relocation

START Date: 
March, 2006
END Date: 
March, 2007

 

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
400

Senior Quantity Surveyor/Contract Administrator, Ministry of Works & Transport, Bahrain, Roads, Bridges and High Pressure Relocation

START Date: 
March, 2006
END Date: 
March, 2007

 

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
400