Planning and Scheduling Engineer

Planning and Scheduling Engineer, Vijay nirman company, Jindal Praxair oxygen plant

START Date: 
August, 2006
END Date: 
November, 2010

Project Planning & Scheduling.
Plan V/s Progress monitoring and tracking
Resource planning & forecast
Budget preparation and monitoring ( Cashflow )
Project Delays & Analysis.
Project Claim management support.

Planning and Scheduling Engineer, Samsung Engineering Co., Carbon Dioxide Capture & Injection Facilities at Uthmaniyah

START Date: 
August, 2011

Project Engineer specialized in Planning, Monitoring & Control.

Planning and Scheduling Engineer, Chiyoda Corporation, QCS Project Construction of Train-6 & 7

START Date: 
June, 2007
END Date: 
April, 2008

Construction Planning & Scheduling Engineer for the Project Director of the entire joint venture project. Provides construction planning support to the project management team which includes but not limited to:

 

§  Monitor and evaluate subcontractor’s level-4 schedule.

§  Conduct periodic feasibility study to determine the schedule’s discrepancies to Chiyoda’s standards.

Planning and Scheduling engineer, HICAPS, UNC A&T State University, Morrison Hall Dormitory Renovation

START Date: 
April, 2004
END Date: 
July, 2005

Working with the Contractor and subcontractors facilitated the development of the baseline construction schedule using planning information. Provided bi-weekly updates and summary narrative reports detailing the longest/critical driving paths, performance analyses, suggestions to improve and/or avoid potential impacts for immediate timeframe and projected timeframe.  

Planning and Scheduling Engineer, HICAPS, Guilford Technical Community College, Technical Education Center

START Date: 
April, 2004
END Date: 
June, 2004

Working with Contractor, faciltated the development of the Contractor's baseline schedule.

Planning and Scheduling Engineer, HICAPS, Oak Ridge Elementary School. New Construction. Renovation

START Date: 
April, 2004
END Date: 
November, 2005

Working with the Contractor and subcontractors facilitated the development of the baseline construction schedule. Provided bi-weekly updates and summary narrative reports detailing the longest/critical driving paths, performance analyses, suggestions to improve and/or avoid potential impacts for immediate timeframe and projected timeframe.  

Planning and Scheduling Engineer, HICAPS, St Pauls Episcopal Church

START Date: 
August, 2002
END Date: 
December, 2004

Working with the Contractor and subcontractors facilitated the development of the baseline construction schedule using planning information. Provided bi-weekly updates and summary narrative reports detailing the longest/critical driving paths, performance analyses, suggestions to improve and/or avoid potential impacts for immediate timeframe and projected timeframe.  

Planning and Scheduling Engineer, HICAPS, UNCG Forney Building Renovation

START Date: 
September, 2007
END Date: 
December, 2008

Working with the Contractor and subcontractors facilitated the development of the baseline construction schedule using planning information. Provided bi-weekly updates and summary narrative reports detailing the longest/critical driving paths, performance analyses, suggestions to improve and/or avoid potential impacts for immediate timeframe and projected timeframe.  

Planning and Scheduling Engineer, HICAPS, Phase 1 High School New Construction and Phase 2 Middle School HAZMAT abatement, demolition, new construction and renovation

START Date: 
December, 2011

Working with Contractor and their subcontractors, facilitated the development of a cost loaded baseline construction schedule. The project consists a new construction high school, Owner occupies new building and moved out of existing elementary school. Contractor commences to abate hazardous materials, extensive demolition, new construction and renovations.

Planning and Scheduling Engineer, HICAPS, Winston-Salem Baseball Stadium

START Date: 
March, 2008
END Date: 
February, 2010

Facilitated the development of and maintained the construction schedule for a $50M minor league baseball stadium. Developed the baseline construction schedule using planning information provided by the Owner, Designer and Contractor.