Phase 1 High School New Construction and Phase 2 Middle School HAZMAT abatement

Planning and Scheduling Engineer, HICAPS, Phase 1 High School New Construction and Phase 2 Middle School HAZMAT abatement, demolition, new construction and renovation

START Date: 
December, 2011

Working with Contractor and their subcontractors, facilitated the development of a cost loaded baseline construction schedule. The project consists a new construction high school, Owner occupies new building and moved out of existing elementary school. Contractor commences to abate hazardous materials, extensive demolition, new construction and renovations.