Planner / Project Controller

Planner / Project Controller, HABAU PPS PIPELINE SYSTEMS, Totea Deep Development engineering contract and Wellhead compression in Bulbuceni

START Date: 
January, 2012
END Date: 
February, 2014

-       Planning, organizing and controlling all project activities to ensure achievement of its objectives under budget. (Primavera software)

-       Vendor/Subcontractor planning review and supervision.

Experience Hours (Planning & Scheduling): 
4150
Experience Hours (Cost Management): 
4150
Experience Hours (Forensic Analysis): 
4150

Planner / Project Controller, Jacobs Engineering, B30 Waste Retrievals

START Date: 
May, 2013

I currently work for Jacobs Engineering where I completed my apprenticeship in Project Controls in September of last year.  During the first year of my apprenticeship I was situated at NETA Training.  During this year I studied project control principles.  Alongside learning these principles I ran a simulated project as part of a team, which took me through the whole project life cycle.  After this I was situated in the Stockton office of Jacobs (formally Aker Solutions).  During this period I rotated around four project control departments.

Planner / Project Controller, Nasb Niroo Co., Karoon III Power Plant Project

START Date: 
August, 1999
END Date: 
June, 2001

Reporting by MS Excel for Engineering

 Karoon III Power Plant Project, as project controller in site (Tehran Office)

Planner / Project Controller, GSK, GSK Block Drug Rationalisation

START Date: 
May, 2000
END Date: 
June, 2006

Project Description

To install additional capacity for, and transfer of, toothpaste & mouthwash production from 2 donor factories, to allow rationalisation, plus numerous smaller projects along similar lines.

Role & Responsibilities
Planning and reporting of installation works, enabling works (logistical process changes, toothpaste formulation development and product rationalisation), and managed transfer of production

Experience Hours (Planning & Scheduling): 
12000