Lead Planner / Senior Planner - London., Bombardier Transportation, SSR ATC

START Date: 
October, 2011
END Date: 
July, 2012

Main clients/Projects:

  • SSR ATC (Automatic Train Control project for LU) signalling upgrade  – NEC3 contract

 

Responsibilities:

  • Acting as a lead planner on circa £350 million signalling project
  • Coordination of planner's work across 3 main sites in Europe and US
  • Managing the programme of over 12 000 activities comprising of 3 major workstreams and incorporating subcontractor’s schedules
  • Monitoring and updating progress of the project (EV, Dashboards etc.)
  • Managing

1.“planning engineer” or “project planner” or “project controller” or “project controls” or “delay analysis”, Al Jawza Project Management & Engineering Consultants, Awaiting new work

START Date: 
July, 2012

I have worked on heavy civil projects on Roads & Infrastuctue works in the Middle East (UAE). I have also worked on a mutistoried stucture project in India (Kerala). Recently I was involved in  the interior renowation and landscaping works of a residential house in India. In my 9 years professional run as a Civil Engineer, I have explored several facets of Engineering and Management.

1.“planning engineer” or “project planner” or “project controller” or “project controls” or “delay analysis”, Al Jawza Project Management & Engineering Consultants, Awaiting new work

START Date: 
July, 2012

I have worked on heavy civil projects on Roads & Infrastuctue works in the Middle East (UAE). I have also worked on a mutistoried stucture project in India (Kerala). Recently I was involved in  the interior renowation and landscaping works of a residential house in India. In my 9 years professional run as a Civil Engineer, I have explored several facets of Engineering and Management.

1.“planning engineer” or “project planner” or “project controller” or “project controls” or “delay analysis”, Al Jawza Project Management & Engineering Consultants, Awaiting new work

START Date: 
July, 2012

I have worked on heavy civil projects on Roads & Infrastuctue works in the Middle East (UAE). I have also worked on a mutistoried stucture project in India (Kerala). Recently I was involved in  the interior renowation and landscaping works of a residential house in India. In my 9 years professional run as a Civil Engineer, I have explored several facets of Engineering and Management.

1.“planning engineer” or “project planner” or “project controller” or “project controls” or “delay analysis”, Al Jawza Project Management & Engineering Consultants, Awaiting new work

START Date: 
July, 2012

I have worked on heavy civil projects on Roads & Infrastuctue works in the Middle East (UAE). I have also worked on a mutistoried stucture project in India (Kerala). Recently I was involved in  the interior renowation and landscaping works of a residential house in India. In my 9 years professional run as a Civil Engineer, I have explored several facets of Engineering and Management.

Senior Planning & Scheduling Engineer, WorleyParsons, Integrated Gas Development (IGD) Project – Das Island

START Date: 
November, 2009
END Date: 
November, 2011

 

B. Integrated Gas Development (IGD) Project – Das IslandThe project involves both offshore and onshore works with building new jetties, jackets, breakwater and flaring facilities on the offshore part and building most of the facilities to be built on the newly reclaimed area of land which will house the 3 trains for Gas dehydration and Compression interlinked with the existing utilities.

Lead Planner / Scheduler, Transfield Services Australia, FCCU

START Date: 
July, 2009
END Date: 
October, 2011

Shutdown Planner

The primary purpose of this role was to estimate, plan and schedule all work activities for the 2011 shutdowns at the Caltex oil refinery, Kurnell.

Rheniformer Unit (CDU Cluster):

Duration                39days

Magnitude             48,296mhrs

Budget Cost          $13.5m

Fluid C

PLANNING ENGINEER, CCFE, Joint European Torus (JET)

START Date: 
October, 2009
END Date: 
September, 2011

Project planning, updating, costing and change control for MAST nuclear fusion experimental reactor.  Earned value and critical path analysis on the MAST Upgrade project in addition to interface management and risk identification /management.  Project monitoring and resource management for Joint European Torus (JET).

Contracts & Planning Manager, Stocks and Stocks, (various projects)

START Date: 
December, 1992
END Date: 
January, 1989

I started working for Stocks and Stocks immediately after qualifying with my B.Sc. Building Management degree in Mmabatho.

My first role as Site Agent (1989)was to plan and set up a new contract to construct a Teachers Training College in  Lehurutse which is just outside Zeerust. Planning was done by hand on A1 sheets of paper and I created two type programmes - a convential gantt chart for the main buildings and a "Line of Balance" chart for the sudent accommodation section.

Lead Planning & Project Control Engineer, Hyder Consulting Middle East Ltd, Lusail

START Date: 
July, 2003
END Date: 
July, 2012
Alfon is responsible for the scheduling management of projects within his team. Alfon’s experience in the Middle East has seen him involved in large scale iconic developments throughout the Gulf region and he has applied international practice codes from the USA, the UK and the Middle East. Alfon has high level experience working with various software packages such as Primavera P6.2 and MS Project.