Joint European Torus (JET)

PLANNING ENGINEER, CCFE, Joint European Torus (JET)

START Date: 
October, 2009
END Date: 
September, 2011

Project planning, updating, costing and change control for MAST nuclear fusion experimental reactor.  Earned value and critical path analysis on the MAST Upgrade project in addition to interface management and risk identification /management.  Project monitoring and resource management for Joint European Torus (JET).

Lead Planner, First Wall, UKAEA, Joint European Torus (JET)

START Date: 
July, 1997
END Date: 
July, 1998

Responsible for all First Wall related planning activity associated with the leading research project into power generation via Nuclear Fusion, involving:

  • Development of detailed level 3 and 4 networks to cover all aspects in preparation of ( and during) interventions and planned shutdowns of the Torus machine.
  • Production of detailed schedules covering all aspects of the required logistics to support Remote Operations during the Shutdown.
  • Production of long term plans for work package co-ordination and resourcing purposes.
  • Resourcing of the progr