Sr. Planning Engineer

Sr. Planning Engineer, Head of Planning Department, JC Maclean International, Shoreline Apartmets, Company Projects Portfolio

START Date: 
May, 2006
END Date: 
May, 2008

JC Maclean International is a leading Manufacturing and Interior fit-out contracting company based in Jabel Ali Free Zone, specializing in executing and providing complete Turnkey solutions for Hotels, Palaces, Private Residences, Commercial Properties etc.

Job Profile         :

- Beginning of 2007 was promoted to a Senior Planning Engineer, managing the planning depart

Sr. Planning Engineer, Bin belaila contracting company, High rise Buildings

START Date: 
May, 2000
END Date: 
November, 2010

I am Sr. Planner with total 10 years experience in Construction field definitely High rise building ,Hotels ,Complex villas.

Currently i am based DUBAI.

My Sole Roles:

1. Assisist and co-operate in preparing Planning and controlling system.

2.

Sr. Planning Engineer, Shell Canada Ltd., Athabaska Oil Sanads Project Expansion

START Date: 
August, 2003

¨        Prepared contractually required planning, scheduling and control procedures for BP Global- NA offshore Project, SNC Lavalin- Kirby project, and for Shell Canada – Carmon Creek & AOSPE Project.

¨        Issued the WBS, resource loaded schedules, and labour plans as part of project controls dept.

Sr. Planning Engineer, EllisDon Construction Inc., Dubai, U.A.E., Badrah Development, Dubai Waterfront

START Date: 
April, 2008
END Date: 
May, 2009
    • Master ScheduleDevelopment& Control to ensure proper Scope/ Integration/ TimeManagement of the project in Coordination with Client / Consultants & Contractors at all levels.
    • Recovery Programmes (Up to required levels).
    • Progress Monitoring, Updating Schedules, Computing Variance and suggesting remedial actions.
    • Implementation of Project Control Procedures.
    • Generation / Updating of Progress S-Curves.
    • Preparation of Progress Report (Weekly & Monthly)
    • Correspondence to client, consultant

Sr. Planning Engineer, ACWA Emirates L.L.C., Dubai, U.A.E. (part of Consolidated Contractors Company CCC Group), Engineering Procurement Construction Contract for (02) Reverse Osmosis Sea Water Desalination plants at the Palm Jumeirah Island

START Date: 
July, 2006
END Date: 
April, 2008
  • Baseline ScheduleDevelopment& Control to ensure proper Scope/ Integration/ TimeManagement of the project in Coordination with Projects Manager, Consultant / Client / Sub-Contractors & Vendors at all levels.
  • Recovery Programmes (Up to required levels).
  • Progress Monitoring, Updating Schedules, Computing Variance and suggesting remedial actions.
  • Implementation of Project Control Procedures.
  • Generation / Updating of Progress S-Curves.
  • Procurement planning including long lead items.
  • Enterprise Resource P

Sr. Planning Engineer, Dar al Riyadh consultant, King Abdullah Financial District, Riyadh, KSA

START Date: 
May, 2009
  • Baseline ScheduleAnalysis / Control to ensure proper Scope/ Integration/ TimeManagement of the project in relation to the contract documents.
  • Progress Monitoring, Updating Schedules, Computing Variance and suggesting remedial actions.
  • Generation / Updating of Progress S-Curves.
  • Tracking status of Submittals and Approvals for Drawings, Materials & Sub-Contractors.
  • Preparation of Progress Report (Weekly & Monthly)
  • Correspondence to client, consultants & contractors relevant to schedule in accordance with Specific /

Sr. Planning Engineer, KOCACHE ENTERPRISES (Under Saudi Oger Sponsership), Demolition & Renovation Works ● 200-Rooms / Beds of Redison SAS Hotel - Riyadh● Various floors of Sherton Hotel - Dammam ● Other $ 210 Millions (Riyadh - KSA)

START Date: 
June, 2004
END Date: 
May, 2005

● Planning, Scheduling, Progress Tracking Updating, Monitoring, controlling & Reporting in liason with client consultant & sub contractors                                                

● TIA - Time Impact Analogies                    &nbsp

Sr. Planning Engineer, SAAD TRADING & CONTRACTING CO. (S.T.C.C), Various Projects for ● Aramco ● University ● Municipality $ 300 Millions (Jeddah KSA)

START Date: 
February, 2001
END Date: 
November, 2002

C P M   -   B a s e d   P la n n i n g ,    S c h  e d u l i n g ,    P r o g r e s s   T r a c k i n g ,   U p d  a t i n g ,

  R e p o r t  i n g   &   C o n t ro  l l i n g 

Sr. Planning Engineer, Saudi Oger Ltd., Pension Fund Office Building (Dabbab Towers) Riyadh K.S.A $ 150 Millions

START Date: 
August, 2005
END Date: 
February, 2008

Planning     Monitoring      Controlling    &     TIA    (Time Impact Analysis)

Sr. Planning Engineer, Al Ahmadiah Contracting & Trading, Al Hamra Firdous Mixed Use complex - Tower 415 Mtr

START Date: 
June, 2005
END Date: 
November, 2007

Worked as Sr. Planing enginner for their project.

The project was a challenging one of having 85 Floors with 415 Mtr height, inclduing multilevel carpark and Shopping mall with Multiplex theater