Developing the Overall Project Planning Package based on the client requirements which includes Work Breakdown Structure (WBS) and Weightage of each WBS, Baseline Schedule in Primavera P6, Overall and Discipline wise “S” curves, Developing Overall Progress Measurement System(Automated System in excel), Engineering Drawing Deliverables Control Register(EDDR), Procurement and Manufacturing Status and Delivery log, Construction PMS, Manpower Histogram, Manpower loading, resource/commodity loading etc.
Recruited to assist in the programming and scheduling for the development of the Serene project, in which FiatAvio intends to build gas turbine based cogeneration systems to provide electric power and process steam to Fiat facilities located at various sites in Italy, mainly in the South.
Responsible for planning and reporting on the 380/132 kV Substation 9009 project, consisting in 30 bays of 380 kV Gas Insulated Switchgear and 14 bays of 132 kV Gas Insulated Switchgear.
Recruited during the installation phase of the thermoelectric power plant CET3 (no. 3 gas turbines Nuovo Pignone of 115 MW and no. 3 steam turbines Ansaldo Industria of 85 MW) inside the Ilva steel works mill at Taranto. This is an innovative plant: a combined cycle fed by recovery fuel gases, produced by the steel work process, provided with a post-firing system.
Combined cycle plant of 115 MW comprising two gas turbine generators Nuovo Pignone of 40 MW, a steam turbine General Electric of 35 MW, two heat recovery boilers, electrical high and low voltage systems, transformers and a distributed control system. Including fuel transfer and purification systems, feed water make-up and storage tanks, demineralising plant, sea water screen and pumping system. Responsible for the preparation and maintenance of the project schedule, review and comment on Contractors schedules and progress. Preparation of weekly and monthly progress reports.
Prepare and Update Various Registers pertaining to Engineering Deliverables, Procurement services, Manufacturing, Sub Contracting & Construction
Recording Progress of all discipline and Updating the schedule developed and monitoring it with the Project Baseline Schedule
Report generation on daily, weekly and monthly basis speaking on Achievements, Critical Issues, Schedule Analysis, Progress Analysis, Front Analysis and Resource Analysis
Main responsibilities:(1) Being responsible for development and management of plan and cost in the company's infrastructure projects;Achievements:(1) To ensure that the scope of schedule and cost are under control for the company infrastructure project;(2) Establishing standardized infrastructure project management system;
Main responsibilities:(1) Being independent management of project plan,schedule and progress;(2) Being responsible for the planning of milestones, critical path, special control progress for project control system;(3) Being responsible for development and management of all level schedule ;(4) Being responsible for measurement of the project progress ;(5) Being responsible for monitoring progress by using physica