1. Prepare baseline schedule (Work Breakdown Structure, activity durations, activity logic relations, resource loading-manpower, equipment, cost) using Primavera P3 or Primavera P6 v.0).
2. Derive by computing from involved quantity/ties activity durations using company productivity standards(if data is available)
or by using available data posted in Planning Planet, expert or experience-based data.
3. Updating data in Primavera from Excel Spreadsheet uploaded site (physical % - complete/approved) progress %ages.