Civil construction planning engineer, Hazama Corporation, Taisei Corporation, Group 3 Engineers Contractors L.L.C., Cement Plant, Hydroelectric projects, Water Supply Piping, Tanks & Pump House, Building Construction.

START Date: 
June, 1987

 

 

GROUP 3 ENGINEERS CONTRACTORS LLC.      

General  Contractor, Abu Dhabi UAE - Since November 2005 up to Present (6 years)

Working as Planning Engineer

  • Prepare Baseline Schedule for tender.
  • Coordinate with Construction Manager and Prepare the Internal Construction Schedule for the Particular Project.
  • Prepare all necessary reports required by the consultant & client.
  • Prepare the Progress measurement Calculation.

 

TAISEI CORPORATION

General Contractor, Abu Dhabi UAE - From October 2002 to October 2005 (3 years)

Project Name : ADWEA Shuweihat Water Scheme Project  (Lot D)

Working as Progress Control & Planning Engineer

  • Coordinate with Construction Manager and Prepare the Internal Construction Schedule.
  • Monitor and update the Baseline Schedule in weekly basis.
  • Prepare calculation sheet for progress measurement.
  • Prepare works schedule, weekly, monthly.
  • Prepare weekly and monthly reports according to the contract requirements.
  • Prepare daily accomplishment report.
  • Coordinate the related works with the different subcontractors.
  • Prepare breakdown of main activities according to bill of quantity.
  • Support and assist claim preparation.

 

HAZAMA CORPORATION

General Contractor, Nepal, Indonesia and Philippines - From February 1991 to November 2001 (10 years)

Project Name :   Luisita Industrial Park 2 – Philippines (3 years)

                         Kotapanjang Hydro Electric Power – Indonesia (5 years)

                         UdaipurCement Plant – Nepal (2 years)     

Working as Progress Control & Planning Engineer

  • Coordinate with Construction Manager and Prepare the Internal Construction Schedule.
  • Monitor and update the Baseline Schedule in weekly basis.
  • Prepare calculation sheet for progress measurement.
  • Prepare works schedule, weekly, monthly.
  • Prepare weekly and monthly reports according to the contract requirements.
  • Prepare daily accomplishment report.
  • Coordinate the related works with the different subcontractors.
  • Prepare breakdown of main activities according to bill of quantity.
  • Support and assist claim preparation.

 

KUME ARCHITECTS ENGINEER (CONSULTANT)

From June 1987 to January 1991 (4 years)

Working as Site Inspector

  • Responsible for all inspections – the accuracy work perform by the Contractor.
  • Inspection of site activities – civil, mechanical and electrical works.
  • Inspection of main materials at the plant before delivery at site
  • Monitor all the materials base on the specification and drawing required
  • Prepare weekly and monthly reports according to the contract requirements.