Baseline from another File or Excel
Forum Sponsor
Top Posters
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
Vasat, Chuck the data into Turbo-Chart (https://turbo-chart.com) and it'll allow you to see two scehdule datasets on one chart.
Hi Alexandre,
Thank you for your response.
As I came to find out, there doesn't seem to be a way to do it the way I described.
My work around was to save the baseline in TILOS and progress the activities based on the other.
Cheers,
Hi Vasat,
I hoped that somebody had the solution, but I was wrong. I have found nowhere in Tilos the way to copy the schedule of one project to make it the baselin of another one, as it is possible in Primavera or Asta Powerproject
When you baseline a project, my experience is that you can only select activities in the current project.
Did you ask the question to Tilos people?
All the best,
Alexandre