Dear all,
I'm currently have 11.01.28 version of Spider Project.
In general I'm impressed with the overall performance and easiness of Spider Project.
Recently only I started working in Spider with a programme having actuals.
I noticed that there might be an error / wrong scheduling calculation and I wanted to share it with you in order to help me understand this issue, and if this calculation is different in newer versions.
I have created a sample programme which you can find it attached here.
In this programme we have 3 activities all with 24 days duration starting 17-Feb-2020.
2 simple links between them:
- Activity 1 --- FF (6 Days) ---> Activity 2
- Activity 2 --- SS (0 Days) ---> Activity 3
Data date 04-March-2020, Activity 1 actuals as planned, Activity 2 changed to 90% complete, Activity 3 no actuals.
In scheduling options we have 4 options to choose in case of out of sequence execution.
First I want to mention that we currently don't have out of sequence execution above, so none of the above options would be our case.
For first link none of the activities have finished so the logic is correct and when Activity 1 will finish, activity 2 to finish 6 days later.
For the second link, Activity 2 has started and Activity 3 not yet and will start after Activity 2, the soonest possible.
I would expect Activity 2 to finish 6 days after Activity 1 finishes and Activity 3 to start just after my Data Date, that is, 05-March-2020.
I can't get the expected result with any of the above options selected:
- Option 1 - Retained Logic: It pushes Activity 3 to start after Activity 2 finishes. Like there was link:
Activity 2 --FS0--> Activity 3
- Option 2 - Retained Logic With Exception Of Activities In Progress: It shifts Activity 2 to finish As early as possible breaking logic between Activity 1 & 2 of FF (6 Days), and keeps Activity 3 as before with no logic at all
- Option 3 - Ignore Preceding links if Activity is in progress: Activities 1 & 2 as Option 2 and Activity 3 to start 05-March-2020 as expected (but Activity 2 not as expected)
- Option 4: Ignore Preceding links of activities finished: Activities 1 & 2 as expected, Activity 3 to start when the remaining of Activity 2 starts and not 05-March-2020
Can you please clarify the above simple scenario?
Is this a mulfunction of my current version, that is 11.01.28, or there is something that I don't get and you can clarify?
Link To File: test-ret-log.002.sprj
Kind Regards,
Alexandros Kroustis
Replies