interested in others thoughts on:
- top down vs bottom up scheduling, which do you use and why
I have always scheduled bottom up and sanity checked the results against what the project manager/project engineers expectations are. Currently there is a push in my company to top down schedule and progressively add logic to all levels of the schedule, the lowest level of logic is to be at work package level, and tasks below that must only be linked within the work package - which to my mind is not really going to work too well.
- do you allow logic at multiple levels of the schedule
I ensure that all logic is at the lowest level, this allows for the critical path to be visible at the activity level, I also find that having logic at multiple levels causes endless issues when progressing not to plan and locating issues within the schedule.
- your thoughts on Finish to Start logic with negative lag
This has to be one of my pet hates, except for scheduling in procurement lead times, even then I generally drive the purchasing activity from another predecessor eg design review and have the successor with the +ve lag (lead time) where possible.
would love to hear thoughts on this from other experienced schedulers.
Thanks
J
Replies