Vladimir,
I have downloaded the new release of spider, very eager to try the features, especially the new milestones wich should not be considered into project scheduling. Unfortunetely I haven't been able to get them to work. There is also the posibility that I don't understand how they work.
I placed some milestones to simulate the cashflow between expenses and revenues (from the payed invoices), some of these milestones will, in all situations, surpass the finish date of the project. After this I unchecked the box "consider into scheduling". After Sheduling (with constraints) even though the project shedule doesn't change, from before adding the milestones I don't get a critical schedule, only the last milestone being considered critical. The only way I found to see the critical schedule is to se a NLT contraint to the last activity of the project.
What am I doing wrong?
PS: what does the Perform Automatically checkbox?
Best Regards,
Bogdan
Replies