Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Controlling discovery & extra work

5 replies [Last post]
Floris Gering
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 30 Jul 2014
Posts: 27

One of the characteristics of turnaround projects is the change of scope due to inspections during execution.

My questions:

  • What is in your experience the best way to deal with discovery and additional work ?
  • How do you incorporate these daily found extra items in the current schedule ?
  • Can they drastically change the critical path ?
  • How often is a rescheduling considered as best practice ?
  • How can people in the field do their job without loosing confidence in the schedule or forecast for the next 3 days, when after a reschedule, due to the extra work discovered, the forecast looks completely different ?

Replies

harshak 10794
User offline. Last seen 5 years 36 weeks ago. Offline
Joined: 21 Feb 2019
Posts: 2
Groups: None

Tutuapp gives an assortment of applications which are paid or not accessible on other application stores, for example, play store or iOS application store. The quality given by this application is awesome. 

SAADI karim
User offline. Last seen 8 years 1 day ago. Offline
Joined: 5 Oct 2015
Posts: 4
Groups: None

Ciao,

   In the STO's execution phase you will face the additional works, So to incorporating these activities on the schedule you have to be sure that these activities will not affecting the late finish date of the shutdown, otherwise you can keep these works for the next shutdown.

But about how to be sure that these additional activities will not delay the project, you have to make a leveling resources in keeping the same priorities by area by systeme.

 

Regards,

K.SAADI

SAADI karim
User offline. Last seen 8 years 1 day ago. Offline
Joined: 5 Oct 2015
Posts: 4
Groups: None

Ciao,

   In the STO's execution phase you will face the additional works, So to incorporating these activities on the schedule you have to be sure that these activities will not affecting the late finish date of the shutdown, otherwise you can keep these works for the next shutdown.

But about how to be sure that these additional activities will not delay the project, you have to make a leveling resources in keeping the same priorities by area by systeme.

 

Regards,

K.SAADI

Mike Testro
User offline. Last seen 33 weeks 8 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Floris

It is standard practice for extra work to be added to the programme as task bars.

They may affect the critical path.

Rescheduling should be done as often as is necessary.

Best regards

Mike Testro

Floris Gering
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 30 Jul 2014
Posts: 27

Nobody ?