Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Multiple imports of risks to Primavera P6

1 reply [Last post]
Dejan Kezic
User offline. Last seen 1 year 36 weeks ago. Offline
Joined: 21 Mar 2018
Posts: 6
Groups: None

Hi everyone,

Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?

Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in P6 to export file to Excel, then prepare it for importing by coping risks to different activities and return it through import.

I have tried it, but I can not find Risks in Available Options in Export dialogues.

 

Thank you in advance!

Replies

Bhavinbhai Lakhani
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 24 May 2024
Posts: 31
Groups: None

Hello Dejan,

 

I think currently, Primavera (P6) does not natively support exporting and importing risks directly through Excel in the same way it does for activities and resources. To achieve this, you typically need to manage risks within P6 itself rather than using Excel as an intermediary for direct risk import.

 

Hope it would help you.

Thanks