What I thought was going to be a trivial exercise is proving to be anything but. What I wanted to do was model the impact of expected rain days. Constructing the calendar was relatively easy using average rainfall and subtracting the number of Saturdays in the month in question then ranging the result. Assigning the calendar was also relatively easy as long as I did it on a single activity. The problem arises when trying to assign the calendar to multiple activities. According to the Oracle Knowledgebase 1277399.1, a global assignment is not possible to a resource-loaded schedule.
My question: Does anyone have a work-around? Pre-assigning the resource via P6 8.2 does not work, or at least not the way I did it. Any thoughts appreciated. Thanks
BTW: This is an intermediate step to avoid using a weather allowance activity. Once I determine the impact of rain days, I was going to modify my Budegeted Units to achieve the P80 finish date in P6 and then apply various Risk Factors to the resulting xer file to get the 'final' result, then determine the relative impact of each factor via the Hulett Method.
Replies