Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Help in Design Variation Order

2 replies [Last post]
Abbas Mahmoud
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 9 Sep 2015
Posts: 3
Groups: None

Hi all;

 

i recently joined a new company (developer), and they have a project in detailed design stage. the consultant have submitted the detialed design in full and our managment have a new requirements which will affect the design massively. the consultnat submitted a design variation order in order to implement the new changes. our contract mentioned only the hourly rate in case of any additional works.

 

Whats is the correct way of calculating the amonut to be paid for the new changes from a developer point of view as our company dont agree with thier new fees?

 

thanks.

Replies

Abbas Mahmoud
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 9 Sep 2015
Posts: 3
Groups: None

Thank Mike.

 

Thats exactly what happened the consultant submitted his offer then we had a detailed discussion and negotiation unitl we agreed on the final fees.

Mike Testro
User offline. Last seen 11 hours 40 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Abbas - Welcome to planning planet.

You say the variations will affect the design massively which implies that a large part of the original design will have to be done again.

There is no "correct" way to calculate the ammount to be paid.

You can ask the designer to break down his fees so that you can check if it is reasonable.

My advice is to negotiate a reasonable fixed fee rather than pay by the hour.

Best regards

Mike Testro